Overview

Phase 1 of construction has started for PVC and metal pipelines with associated valves and appurtenances and the installation of groundwater wells within the Chino Airport. This includes construction of approximately 17,500 LF of 16-inch, 12-inch, 8-inch and 6-inch Raw Water Pipeline, installation of fiber optic communication network, construction of five (5) groundwater pumping wells, equipping ten (10) ground water pumping wells, construction of five (5) monitoring wells, and construction of five (5) well sites with masonry building for electrical equipment.

Project Costs

$20 million

Project Funding

American Rescue Plan Act

Schedule

March 27, 2023 – NTP issued

April 2025 – Anticipated Completion