The Department of Public Works – Special Districts provides the following as a summary update since the January 12 website update:

  • County received bids for Snowdrop Road construction on February 16, 2021. Lowest responsible bid received at $3,612,491.87 from Trinity Construction
  • Regional Water Quality Control Board Permit received on February 18, 2021
  • Western Alliance agreed to provide the County a project bond in the amount of $5,629,026.07
  • County Debt Advisory Committee approved bond on March 18, 2021
  • County of San Bernardino Board of Supervisors approved the project bond on April 6, 2021
  • Staff continue their efforts to meet their targeted time lines of
    • April 15, 2021 Bond Close of Escrow
    • April 20, 2021 Award of Contract
    • May 2021 Construction Start
    • Spring 2022 Construction completion date