Department of Public Works, Special Districts Division is pleased to announce the completion of Snowdrop Road Project. The project entailed construction of 2.1 miles of new asphalt roadway, retaining walls,…
18 results
Category: AD2018-1
Special Districts provides the following as a summary update: Construction is currently focusing on completion of retaining walls and Christmas Canyon drainage and earthworkBiological Monitoring Program continue without noticing any…
All storm drain structures are complete except Christmas Canyon. Construction currently focusing on Slope work and earth grading Storm Water Management Plans were reviewed and implemented completely Upcoming scope: installation…
The Department of Public Works – Special Districts provides the following update since the September Website update: Construction is currently focusing on earthwork and storm drainsConstruction Change Directive has been…
The Department of Public Works – Special Districts provides the following as a summary update since the July update: Construction is currently focusing on slopes grading and concrete work for…
The department of Public Works – Special Districts provides the following as a June summary update since the April 1, 2021 Town Hall Meeting Update.
The Department of Public Works – Special Districts provides the following as a summary update since the January 12 website update: County received bids for Snowdrop Road construction on February…
The Department of Public Works – Special Districts provides the following as a summary update since the August 2020 presentation: An Addendum was prepared to the Environmental Initial Study/Mitigated Negative…
Please see attached presentation for the most recent update. This presentation was presented in a virtual town hall meeting on Aug 26, 2020 Snowdrop Road Status Update 8-26 Final
Project Status The Snowdrop Road Project (Project) was initially approved by the Board of Supervisors to advertise for competitive bids on May 21, 2019. As previously mentioned, shortly after the…